VII. Historic Preservation Fund Grants to Certified Local Governments
D. Application Timetable

As Congressional and DOI schedules and directives allow, the timetable for applications shall be as follows:

  1. DOI notifies North Carolina SHPO of projected annual allocation.

  2. Thirty (30) days later, SHPO notifies CLG of availability of funds.

  3. Sixty (60) days later, SHPO receives applications from CLGs. (Following evaluation and selection process, SHPO submits required Project Descriptions to DOI for project approval and obligation of funds. These activities require approximately sixty (60) days.)

  4. Thirty (30) days after SHPO receives formal obligation of funds from DOI, SHPO notifies local government of grant awards.
* Reproduced for the City of Washington Department of Planning and Development Website from the January 1992 revision of this document.
Return to: [Home]  [Planning & Development]  [Historic Preservation]
[State Historic Preservation Office Documents]
[Certified Local Government Program Guidelines]